Marine LNG Bunkering Manifold, ESD-1 / ESD-2 Ship-Shore Link (SSL), Emergency Release Coupling (ERC) & Pre-Transfer Purging Guide

Practical IGF Code, IGC Code and ISO 20519:2021 guide to LNG bunkering manifolds, ESD-1 and ESD-2 Ship-Shore Links, ERC dry-break couplings and N2 purging.

← All technical guides · Category: LNG FGSS & GVU · Updated: · 12 min read

Key Takeaways (TL;DR)

  • Under the IGF Code (IMO Res. MSC.391(95) Chapter 8, with manifold regulations 8.4.1 to 8.4.3 amended by IMO Res. MSC.551(108) in force from 1 January 2026) and ISO 20519:2021, marine LNG bunkering stations require open-deck natural ventilation or risk-assessed mechanical extraction (8.3.1.1 and 13.7), hull brittle-fracture protection and drip-tray spill management for LNG with an atmospheric boiling point near -162 deg C (8.3.1.3 and 8.3.1.5), manual and remote shutdown valves in series (8.5.3), dry-disconnect manifold arrangements (8.4.1), and an Emergency Release Coupling (ERC) or Emergency Release System (ERS) enabling physical dry break-away unless fitted on the supply side (8.4.3).
  • Both gas-fuelled receiving ships (IGF Code 8.5.7 and 18.4.4.4) and gas-carrier LNG bunker vessels (IGC Code IMO Res. MSC.370(93) 18.10.1.4) rely on a compatible Ship-Shore Link (SSL) to coordinate, in common bunkering practice, an ESD-1 controlled transfer shutdown ahead of any ESD-2 emergency break-away separation, while the statutory 30-second smooth closure rule (IGF Code 16.7.3.6 and IGC Code 18.10.2.1.3) applies to ESD valves in liquefied gas piping systems on the receiving ship (IGF) and in liquid piping systems on a gas-carrier bunker vessel (IGC), alongside the IGF Code 16.7.3.7 remote bunkering overfill valve limit of 3600 * U / BR seconds or 5 seconds, whichever is least.
  • Safe transfer execution depends on a signed pre-bunkering PIC agreement (IGF Code 18.4.1.1.1 as expanded by MSC.551(108)), dry nitrogen inerting and controlled line cool-down to the limits in the approved Fuel Handling Manual (8.5.1, 18.4.2.1 and 18.6), strict compliance with the IGF Code 6.8.1 98% loading limit at reference temperature (noting 6.8.2 and 6.8.3 allow a special higher calculated limit never above 95% only where tank insulation and location make external-fire tank heating probability very small, or under 6.8.2 where a secondary 6.9 pressure-maintenance system independent of fuel consumers is fitted), post-transfer liquid draining and gas-freeing (8.5.4 and 8.5.5), STCW Regulation V/3 Basic and Advanced IGF certification (IMO Res. MSC.396(95)), ISM Code Section 10.3 critical-system testing, and SOLAS Regulation XI-1/7 plus IMO Res. MSC.581(110) enclosed-space controls.

Marine LNG bunkering manifold, SSL ESD-1/ESD-2 and ERC fault symptoms, root causes and immediate verification actions

Observed Symptom / AlarmSubsystemPrimary Mechanical or Control CauseImmediate Shipboard Verification & Action
SSL handshake fault or intermittent link dropout before cool-downShip-Shore Link (SSL) & ESD-1 loopMismatched optical, electric multipin or pneumatic SSL interface types, moisture or frost on fibre ferrules/pins, or open fallback loopWithhold LNG admission (IGF Code 18.4.4.1), inspect and dry SSL connectors in a safe state, verify interface compatibility (18.4.4.4), and prove bidirectional ESD-1 trip signals between ship and bunker source before signing the bunker safety checklist (18.4.3.1.1)
Liquid-line ESD valve exceeds 30-second stroke or closes jerkinglyManifold remote shutdown valve (IGF 8.5.3 / 16.7.3.6)Low pneumatic/hydraulic actuator supply pressure, iced stem gland packing, restricted quick-exhaust pilot port, or degraded solenoid pilotAbort transfer preparation, time full-open to full-closed travel against the onboard valve-closure record (30-second maximum for ESD valves in liquefied gas piping under IGF Code 16.7.3.6, and in liquid piping under IGC Code 18.10.2.1.3), restore actuator air/hydraulic supply, and record the repair in the planned maintenance system (ISM Code 10.2, with the valve treated as critical equipment under 10.3)
Localised frosting, vapour plume or drip-tray sensor alarm at manifoldDry-disconnect coupling, flange or ERC seal (IGF 8.4.1 / 8.4.3)Ice particles or debris trapped on cryogenic lip seal during hook-up, excessive hose bending load on presentation flange, or thermal shock from rapid cool-downInitiate manual ESD-1 stop immediately, maintain hull water curtain to protect deck plating against -162 deg C brittle cooling (8.3.1.5), drain liquid and nitrogen-purge the spool (8.5.1 and 8.5.4), and inspect hose saddles and seal faces only after confirming a gas-free state
High residual oxygen or elevated moisture dewpoint during pre-transfer purgeNitrogen (N2) inerting & purging header (IGF 8.5.1 / 18.6)Saturated nitrogen generator membrane or low N2 receiver pressure, wet service-air cross-leakage, or unpurged dead leg between manifold and double-block valvesHold cool-down (18.6.2), verify onboard nitrogen purity, pressure and dewpoint against the approved Fuel Handling Manual (18.2.3), repeat pressure-release or sweep purge cycles across every manifold branch until Fuel Handling Manual targets are met, and prevent air ingress
High tank pressure trend or premature high-level alarm during topping-offTank monitoring & overflow control (IGF 15.4.2 / 16.7.3.7)Insufficient vapour-return flow or BOG consumption, density stratification between warm tank heel and delivered LNG, or excessive topping-off transfer rateStep down transfer rate per the written PIC agreement (18.4.1.1.1), adjust top-spray versus bottom-fill routing using LNG-BDN density and temperature to avoid stratification (the Fuel Handling Manual must describe rollover emergency actions, 18.4.2.1.9), keep filling within the IGF Code 6.8.1 98% reference-temperature curve (or approved 6.8.2/6.8.3 curve), and never vent gas to atmosphere (6.9.1.2 and 8.5.2)
Bunker-duct extraction fan trip or gas alarm in semi-enclosed stationBunkering station & double-wall ducting (IGF 9.5 / 13.7 / 13.8.2-13.8.4 / 15.5)Extraction fan failure dropping below 30 air changes per hour (IGF Code 13.8.1, or below the 3 m/s flow-velocity design alternative in 13.8.4), fouled non-hazardous air inlet mesh (13.8.3), or inner pipe flange leak into annular bunkering duct (9.5.1, or 9.5.3 to 9.5.6 for ships constructed on or after 1 January 2024)Confirm audible/visual ventilation-loss alarm before bunkering starts (15.5.2) and automatic ESD trip on bunkering-duct gas detection (15.5.3, alongside 15.8.6), isolate and nitrogen-purge bunkering lines, evacuate personnel from potential asphyxiant or flammable pockets (18.5.1), and enforce SOLAS XI-1/7 plus IMO Res. MSC.581(110) before entry

1. Bunkering Station Arrangement, Manifold Dry-Disconnect & MSC.551(108) ERC Architecture

Under Chapter 8 of the International Code of Safety for Ships Using Gases or Other Low-Flashpoint Fuels (IGF Code, IMO Res. MSC.391(95) as amended) and ISO 20519:2021 (Specification for bunkering of liquefied natural gas fuelled vessels), the shipboard bunkering station forms the primary physical containment and isolation boundary between the bunker supplier and the vessel fuel storage system. IGF Code 8.3.1.1 requires the bunkering station to be positioned on open deck with sufficient natural ventilation, while closed or semi-enclosed bunkering stations undergo special risk-assessment consideration (4.2.2) and require dedicated ventilation under 13.7 to discharge any released vapour safely outside. Where fuel piping runs inside ducts or double-wall pipes, IGF Code 13.8.1 requires extraction ventilation of at least 30 air changes per hour (13.8.4 allows a lower rate only if a flow velocity of at least 3 m/s is ensured with the fuel pipes and components installed), with the inlet taken from a non-hazardous area and protected by a wire mesh guard against water ingress (13.8.3). For ships constructed on or after 1 January 2024, IMO Res. MSC.458(101) replaced the double-wall rules with 9.5.3 to 9.5.6: gaseous fuel pipes in ventilated ducts (9.5.4), and liquefied fuel pipes in a secondary enclosure able to contain leakage (9.5.6).

Cryogenic spill management and hull steel protection are engineered around the physical behaviour of LNG, which boils at roughly -162 deg C at atmospheric pressure and rapidly embrittles ordinary carbon-manganese deck and side-shell plating on contact. Under IGF Code 8.3.1.2 to 8.3.1.5, manifold piping must be arranged so external mechanical damage cannot breach the ship fuel containment system, arrangements must be provided for safe management of any spilled fuel (8.3.1.3, typically stainless-steel drip trays and drains), and surrounding hull or deck structures must be protected against unacceptable cooling (typically through a continuously running hull water curtain during transfer alongside low-temperature drip-tray monitoring specified in the approved Fuel Handling Manual). In parallel, 11.5.1 to 11.5.3 and 11.5.7 require a fixed water-spray fire-protection system covering exposed open-deck storage tanks and adjacent bunkering station boundaries (at 10 litres/min/m2 for horizontal projected surfaces and 4 litres/min/m2 for vertical surfaces) with remote pump start and valve actuation accessible outside the fire-exposed zone and operable from the remote bunkering control location (15.5.1).

Amended manifold connection rules entered into force on 1 January 2026 under IMO Resolution MSC.551(108), which replaced IGF Code 8.4.1 and added 8.4.2 and 8.4.3. Under revised 8.4.1, the bunkering manifold must be designed to withstand the external loads during bunkering and achieve a dry-disconnect operation through one of three recognised configurations: a dry-disconnect/connect coupling (DDC) to a standard at least equivalent to those acceptable to the IMO (8.4.1.1; industry commonly refers to ISO 21593:2019), a manual or hydraulic connect coupler mated to the presentation flange (8.4.1.2), or a bolted flange-to-flange assembly (8.4.1.3). Under 8.4.2, whenever a ship uses a manual/hydraulic coupler (8.4.1.2) or bolted flange assembly (8.4.1.3) rather than an integral DDC, the hardware must be combined with strict draining and purging procedures that achieve dry-disconnect performance, backed by a design-stage risk assessment (4.2.2) evaluating dynamic manifold loads and documented in the approved Fuel Handling Manual (18.2.3).

To protect against vessel surge, mooring line failure or tug/bunker barge drift-off, IGF Code 8.4.3 (MSC.551(108)) requires an Emergency Release Coupling (ERC) or Emergency Release System (ERS), or equivalent means, enabling a rapid physical dry break-away disconnection in an emergency, unless that ERC/ERS is installed on the bunkering supply side of the transfer line. In typical designs, the ERC sits in series with the transfer hose or loading arm and incorporates opposing self-sealing check poppets or synchronised double ball valves that close both upstream and downstream bores before the shear-pin or hydraulic/pneumatic collar separates. Immediately inboard of the presentation flange, IGF Code 8.5.3 mandates a manually operated stop valve and a remotely operated shutdown valve in series (or a combined manual and remote valve) in every liquid and vapour bunkering line, while 8.3.2.2 requires any ship fuel hoses subjected to tank, pump or compressor discharge pressure to have a bursting pressure of at least five times the maximum bunkering pressure, and 8.5.6 requires positive cross-over isolation so fuel cannot pass inadvertently to the unused side of the ship.

  • Verify spill-management arrangements such as drip trays, hull-protection water curtains (IGF Code 8.3.1.3 and 8.3.1.5) and, where fuel tanks are on open deck, remote actuation of the fixed 10 and 4 litres/min/m2 water-spray system (11.5.1 to 11.5.3, 11.5.7 and 15.5.1) before hose or arm connection.
  • Inspect bunker transfer hoses and saddles against IGF Code 8.3.2.2 (bursting pressure at least five times maximum bunkering pressure), checking pressure-test certificates, cryogenic flexibility, and proper mechanical support to prevent flange over-stressing.
  • Confirm the manifold dry-disconnect configuration (IGF Code 8.4.1.1 DDC or 8.4.1.2/8.4.1.3 coupler/bolted flange per the Fuel Handling Manual risk assessment) and verify that a live, unpinned ERC/ERS dry break-away unit (8.4.3) is fitted on either the manifold or supplier line.
  • Verify electrical continuity and insulating-flange integrity on supplier hoses or arms (IGF Code 18.4.5 and ISO 20519:2021) without bridging insulating flanges with external bonding cables, and confirm unused cross-over valves are locked shut (8.5.6).

3. Pre-Transfer Nitrogen Inerting, Line Cool-Down, 6.8 Loading Limits & Post-Bunkering Purging

Every LNG bunkering operation starts with formal written alignment between the receiving ship PIC and the bunkering source PIC under IGF Code 18.4.1. Under 18.4.1.1.1 as amended by IMO Res. MSC.551(108) (in force 1 January 2026), both PICs must agree in writing before transfer commences on the complete transfer procedure (including cooling down and, if necessary, gassing up), the maximum transfer rate at all stages, the minimum and maximum limiting transfer pressure and temperature, the bunkering-line pressure relief valve (PRV) settings, and the volume to be transferred, alongside written emergency procedures (18.4.1.1.2) and a completed, mutually signed bunker safety checklist (18.4.1.1.3 and 18.4.3.2). Permanently mounted fuel system schematics/P&IDs must be displayed at both the bunker station and the remote bunker control station (18.4.2.2), where tank pressure, tank temperature, tank level, remote manifold/water-spray valves and overfill shutdown status are continuously monitored (15.5.1).

Pre-transfer nitrogen inerting, moisture purging and controlled cool-down protect the manifold from explosion hazards, ice seizure and flange thermal shock. Under IGF Code 8.5.1, 8.5.2 and 18.6.1 to 18.6.2, inerting and purging prevent any combustible gas-air atmosphere from forming inside piping or tanks, prevent air from entering gas-filled piping, and prohibit gas discharge to the atmosphere during storage-tank filling. Never apply guessed universal bar or dewpoint figures across different vessels: sweep or pressure-cycle the coupled hose/arm and manifold spool with dry nitrogen strictly to the oxygen, moisture-dewpoint and leak-test hold pressures specified in the ship approved Fuel Handling Manual (18.2.3) and ISO 20519:2021 interface procedure, ensuring residual humidity cannot freeze ERC poppets or ESD seats when cryogenic flow begins. Once tightness is proven, admit cold natural gas vapour or misted LNG slowly to chill the transfer line within the Fuel Handling Manual cool-down rate limit so differential contraction cannot bow stainless piping or relax presentation-flange gasket stress.

Bulk loading and topping-off must strictly obey the storage-tank filling rules in IGF Code 6.8 and boil-off gas (BOG) pressure-holding rules in 6.9. Under IGF Code 6.8.1, liquefied gas storage tanks must not be filled beyond a volume equivalent to 98% full at the reference temperature (defined in 2.2.36 as the temperature corresponding to the saturated vapour pressure of the fuel at the PRV set pressure), governed by the loading-limit curve LL = FL * (rho_R / rho_L) where FL equals 98%, rho_R is fuel relative density at reference temperature, and rho_L is fuel relative density at loading temperature. Engineers should note the exact scope of IGF Code 6.8.2 and 6.8.3 (where 6.8.3 was added by IMO Res. MSC.458(101) for ships constructed on or after 1 January 2024): a higher loading limit than calculated using the reference temperature (but never above 95%) is a special Administration/Class exception rather than a standard filling limit, permitted under 6.8.2 (the original text, which carries no construction-date limit) only where tank insulation and location make the probability of external-fire tank heating very small or a secondary 6.9 pressure-maintenance system independent of fuel consumers is fitted, and permitted under 6.8.3 (for ships constructed on or after 1 January 2024) strictly where tank insulation and location make the probability of external-fire tank heating very small. Throughout loading, tank pressure must be controlled via top spray, vapour return to the supplier, reliquefaction or approved gas consumers without venting to atmosphere (6.9.1.2 and 8.5.2, alongside the 6.9.1.1 15-day idle pressure-hold capability), while balancing top versus bottom fill lines according to heel versus delivered LNG density to avoid tank stratification and rollover (the Fuel Handling Manual describes the emergency actions, 18.4.2.1.9).

Post-transfer stripping, gas-freeing and fuel quality documentation are equally critical before uncoupling. After stepping down flow rate to complete the agreed volume, crews drain all liquid LNG from pump suctions, hoses and ship bunkering pipes into the storage tank or approved receiver (IGF Code 8.3.1.4 and 8.5.4), warm and sweep hydrocarbons using dry nitrogen, and comply with 8.5.5, which requires bunkering pipes to be inerted and gas-freed, remaining free of gas whenever not engaged in bunkering unless the consequences of not gas-freeing have been formally evaluated and approved. Only after manifold gauges and calibrated portable gas checks confirm liquid-free, depressurised and Fuel Handling Manual purge completion is the coupling disconnected and blanked. Finally, under 18.4.1.2 and the Annex to Part C-1, both PICs sign the LNG Bunker Delivery Note (LNG-BDN) recording methane number (MN), lower and higher calorific values (MJ/kg), Wobbe indices, density (kg/m3), delivered and tank LNG temperatures and pressures, hydrocarbon/nitrogen/sulphur mass percentages plus trace contaminant limits on the Part C-1 Annex form, and net delivered totals (t, MJ, m3 and GJ) so engine-room staff can update dual-fuel or spark-gas knock-control methane number inputs.

  • Execute and sign the MSC.551(108) written pre-bunkering PIC agreement (IGF Code 18.4.1.1.1) specifying cool-down/gassing-up steps, stage rates, minimum/maximum transfer pressures and temperatures, bunkering-line PRV settings, and emergency actions.
  • Purge coupled transfer lines with dry nitrogen to the exact oxygen, dewpoint and leak-test criteria in the approved Fuel Handling Manual (18.2.3 and 18.6.2), and adhere strictly to the manual cool-down rate before bulk LNG transfer.
  • Verify maximum target filling volume against the approved tank loading-limit curve (IGF Code 6.8.1 98% at reference temperature, or Class-approved 6.8.2/6.8.3 special curve where applicable), route top/bottom fill to avoid stratification and rollover (emergency actions described in the Fuel Handling Manual, 18.4.2.1.9), and maintain zero atmospheric venting (8.5.2).
  • Drain all residual liquid LNG (8.5.4), nitrogen-purge and gas-free ship bunkering lines upon completion unless specifically approved otherwise (8.5.5), and verify the signed Part C-1 Annex LNG-BDN (18.4.1.2) including methane number before updating engine control parameters.

4. STCW Reg. V/3 Competence, ISM Code 10.3 Critical Checks & MSC.581(110) Space Entry Precautions

Statutory crew qualification on gas-fuelled ships is governed by IGF Code Chapter 19 (19.2), STCW Regulation V/3 (IMO Res. MSC.396(95)), STCW Code Section A-V/3 (IMO Res. MSC.397(95)), with ISO 20519:2021 also addressing the training and qualification of bunkering personnel. All seafarers must receive ship-specific IGF familiarisation before being assigned shipboard duties (STCW Reg. V/3.3 and I/14.1.5). Crew members with designated safety duties associated with the care, use of, or emergency response to gas fuel must hold a Certificate of Proficiency (CoP) in Basic Training for Service on Ships Subject to the IGF Code (V/3.4, with Basic or Advanced Liquefied Gas Tanker V/1-2 certification accepted under V/3.6). Masters, engineer officers, and all personnel with immediate responsibility for the care and use of fuels and fuel systems, typically including the ship Bunkering PIC, must hold an Advanced IGF Code CoP (V/3.7 and V/3.8, requiring Basic IGF CoP, an approved advanced course, and at least 1 month of approved seagoing service with at least 3 bunkering operations on IGF ships, up to 2 replaceable by approved simulator training, or the V/3.9 route for officers already certified for advanced liquefied gas tanker service, who also meet V/3.6, have completed the bunkering operations or 3 cargo operations, and have 3 months' relevant seagoing service in the previous 5 years), maintained via 5-yearly refresher evidence (V/3.12). Missing or expired STCW Reg. V/3 Certificates of Proficiency are among the deficiencies that may warrant detention under IMO Res. A.1206(34) Appendix 2 (STCW Reg. I/4.2.1), at the Port State Control officer's professional judgement.

Under ISM Code Section 10.3 (IMO Res. A.741(18)), the Company should consider identifying, in the Safety Management System, SSL transceivers, ESD-1/ESD-2 trip loops, 30-second ESD valve actuators (IGF Code 16.7.3.6), ERC break-away assemblies (8.4.3), tank high-level and 16.7.3.7 overfill sensors (including physical fuel-level raising tests at the first full loading after delivery and after every dry-docking under 15.4.2.3), fixed/portable gas detectors, and bunker-duct extraction fans as critical systems whose sudden operational failure may create hazardous situations, backing them with scheduled PMS functional tests. Regular gas-related emergency exercises and tabletop drills under IGF Code Chapter 17 verify crew readiness against the Fuel Handling Manual (18.2.3). Throughout transfer, IGF Code 18.4.6.1 and 18.4.6.2 require fire-safety warning signs at bunkering access points, essential-personnel-only manifold access, appropriate personal protective equipment (18.4.6.2; in practice a face shield, insulated cryogenic gloves, splash-resistant long coveralls and antistatic safety footwear), and immediate transfer stoppage if any required safety condition fails, noting also under 18.4.6.3 and 18.4.6.4 that where portable LNG fuel tanks are used, connecting or disconnecting tank systems during a sea voyage or manoeuvring is strictly prohibited.

Inspection or maintenance inside a Tank Connection Space (TCS), fuel storage hold space, interbarrier space, Fuel Preparation Room, double-wall pipe duct or semi-enclosed bunker station carries severe asphyxiation and flammable-gas risk addressed by IGF Code 18.5.1, SOLAS Regulation XI-1/7, SOLAS Regulation III/19.3.3 (two-monthly enclosed-space entry and rescue drills) and IMO Resolution MSC.581(110) (adopted June 2025, Revised Recommendations for Entering Enclosed Spaces Aboard Ships). Because nitrogen used for line purging (8.5.1 and 8.5.5) displaces oxygen without odour or visible mist and cold methane vapour initially pools in low pockets before warming and rising, crews should lock out all LNG and nitrogen valves, run continuous mechanical ventilation, stop ventilation before testing, and sample at multiple heights using the portable gas detector SOLAS Reg. XI-1/7 requires on board (measuring at least oxygen, flammable gases/vapours, H2S and CO, together with suitable onboard means for its calibration) to verify the recommended 20.9% oxygen by volume, below 1% LFL flammable vapour, below 0.5% carbon dioxide, and toxic contaminants below 50% of the occupational exposure limit under an entry permit whose maximum validity is 8 hours by default and which becomes void if the space is left unattended, remembering that EEBDs are strictly for escape and never for entry.

Class surveyors, Flag State auditors, Port State Control officers (IMO Res. A.1206(34)) and commercial SIRE 2.0 or RightShip RISQ 3.2 vetting inspectors routinely audit SSL pre-transfer checklists (IGF Code 18.4.3), 30-second ESD valve stroke records (16.7.3.6 and IGC Code 18.10.2.1.3), post-dry-dock high-level float/sensor test certificates (15.4.2.3), signed LNG-BDN files (18.4.1.2) and STCW Reg. V/3 CoP matrices. Aligning bunkering watchstanding directly with the vessel approved Fuel Handling Manual (18.2.3), permanently mounted bunker-station P&IDs (18.4.2.2) and ISM Code Section 10.3 test logs prevents costly bunker delays and nuisance ESD-1 trips during tight port calls. For ship-specific LNG bunkering procedure reviews, SSL/ESD fault diagnostics or pre-vetting readiness support, Marvel Solutionz offers remote technical support at $350 USD for a 1-hour consultancy (+ 5% sales tax) alongside practical crew training in the LNG, Dual-Fuel (DF) & Spark-Gas (SG) Academy at $395 USD self-paced (+ 5% sales tax), with Lab 01 as a free 5-minute interactive trial and Labs 02 to 05 in the paid programme, or $3,500 USD (+ 5% sales tax) for Corporate Team Training up to 10 engineers.

  • Verify valid STCW Reg. V/3 Basic (V/3.4) and Advanced (V/3.7 to V/3.9) Certificates of Proficiency, 5-yearly refresher evidence (V/3.12), and ship-specific familiarisation logs (V/3.3) for all officers and ratings assigned to LNG bunkering duties.
  • Track SSL loop checks, 30-second ESD valve stroke tests (16.7.3.6), ERC inspections (8.4.3), and post-dry-dock full-loading high-level alarm tests (15.4.2.3) under ISM Code Section 10.3 critical-equipment PMS routines alongside Chapter 17 gas drills.
  • Enforce access warning signs, essential-staff limits and cryogenic PPE at the manifold (IGF Code 18.4.6.1 and 18.4.6.2), prohibit connecting or disconnecting portable fuel tanks at sea or during manoeuvring (18.4.6.4), and halt transfer immediately upon any safety or communication lapse (18.4.4.1).
  • Lock out nitrogen and LNG lines, verify the portable gas detector SOLAS XI-1/7 requires on board together with its onboard calibration means, conduct two-monthly SOLAS III/19.3.3 rescue drills, and follow IMO Res. MSC.581(110) multi-level testing recommendations (20.9% O2 and below 1% LFL) under an entry permit valid for 8 hours at most by default (void if the space is left unattended) before entering any TCS, hold space or semi-enclosed bunker station.

Frequently Asked Questions

What is the operational difference between ESD-1 and ESD-2 during marine LNG bunkering?

In common LNG bunkering practice, as set out in the ship approved Fuel Handling Manual (IGF Code 18.4.2.1.8), ESD-1 is the primary emergency shutdown stage transmitted across the Ship-Shore Link (IGF Code 8.5.7 and IGC Code 18.10.1.4): triggered manually or by high-high tank level, gas/fire detection, SSL signal loss or stage-1 vessel drift warning, ESD-1 trips transfer pumps/compressors and closes ship and supplier manifold ESD valves cleanly while keeping the hose or arm connected. ESD-2 is the secondary emergency break-away stage triggered by extreme vessel excursion toward the mechanical limit of the transfer assembly, closing isolation valves/poppets and firing the Emergency Release Coupling (IGF Code 8.4.3) to achieve physical dry separation before manifold fracture can occur.

Does the 30-second ESD valve closure requirement apply to vapour lines as well as liquid LNG bunkering lines?

It depends on which Code applies. On a gas-carrier LNG bunker vessel, IGC Code 18.10.2.1.3 (IMO Res. MSC.370(93)) applies the rule to close fully and smoothly within 30 seconds of actuation to emergency shutdown valves in liquid piping systems, with verifiable and repeatable closure-time information available on board. On the receiving gas-fuelled ship, IGF Code 16.7.3.6 (IMO Res. MSC.391(95)) applies the same 30-second rule to emergency shutdown valves in liquefied gas piping systems and does not expressly exclude vapour lines, so follow the closure times in the ship's approved documentation and records. Separately, under IGF Code 16.7.3.7 and 8.5.8, the remote bunkering valve actuated by the independent overfill sensor (15.4.2.2) must close within 3600 * U / BR seconds or 5 seconds, whichever is the least, unless a higher value is shown to be needed to limit surge pressure.

How do the 98% and 95% LNG fuel tank loading limits work under IGF Code Regulation 6.8?

Under IGF Code 6.8.1, liquefied gas fuel storage tanks must not be loaded above a volume equivalent to 98% full at the reference temperature (the saturated vapour temperature corresponding to tank PRV set pressure), adjusted for loading temperature density via the loading-limit formula LL = FL * (rho_R / rho_L). Under 6.8.2 (the original text) and 6.8.3 (added by IMO Res. MSC.458(101) for ships constructed on or after 1 January 2024), a special higher calculated loading limit (never exceeding 95%) is an Administration/Class exception rather than a standard filling limit, permitted where tank insulation and location make external-fire tank heating probability very small (or, under 6.8.2 only, where a secondary 6.9 pressure-maintenance system independent of fuel consumers is installed).

What changed on 1 January 2026 for LNG bunkering manifolds and PIC agreements under IMO Res. MSC.551(108)?

IMO Resolution MSC.551(108) amended IGF Code 8.4 and 18.4.1.1.1 from 1 January 2026. Revised 8.4.1 and 8.4.2 recognise dry-disconnect/connect couplings (8.4.1.1) alongside manual/hydraulic connect couplers (8.4.1.2) and bolted flange-to-flange assemblies (8.4.1.3) when backed by operating procedures ensuring dry-disconnect performance and a design-stage dynamic-load risk assessment in the Fuel Handling Manual (18.2.3). New 8.4.3 mandates an Emergency Release Coupling (ERC/ERS) or equivalent dry break-away device unless fitted on the supply side, and amended 18.4.1.1.1 adds minimum and maximum limiting transfer pressures and temperatures plus bunkering-line PRV settings to the mandatory written pre-bunkering PIC agreement.

Which STCW Regulation V/3 certificates are required for crew conducting LNG bunkering?

Under STCW Regulation V/3 (IMO Res. MSC.396(95)) and Section A-V/3 (MSC.397(95)), all crew require ship-specific IGF familiarisation (V/3.3), seafarers with designated safety or fuel-emergency duties require a Basic IGF Code Certificate of Proficiency (V/3.4, with V/1-2 liquefied gas tanker CoPs recognised under V/3.6), and Masters, engineer officers and all personnel with immediate responsibility for fuel care and bunkering require an Advanced IGF Code CoP (V/3.7 to V/3.9, including approved advanced training plus 1 month seagoing service and at least 3 bunkering operations where up to 2 may be simulator-based, or the V/3.9 gas-tanker experience route), refreshed every 5 years under V/3.12.

Regulatory & Technical Sources

Train with Marvel Solutionz or get expert help

Try the LNG, Dual-Fuel & Spark-Gas simulator free for 5 minutes, then enrol in the Academy: Self-Paced $395 USD or 6-Week Cohort $995 USD (+ 5% sales tax). Or book a 1-hour consultancy for $350 USD (+ 5% sales tax).

Let’s talk about your operation and maintenance.

Enquiries welcome at any time. Book our daily 1-hour consultation at 12:00 PM Central Time (CT) ($350 USD + 5% sales tax) or send an enquiry about your vessel, power plant or project.

ACADEMY MEMBER & CLIENT COMMENTS

Have an Academy Access Key? Sign in on this page to send comments or questions straight to our instructors.