SOLAS II-2/4.5.5.1 (MSC.365(93)) mandates fixed inert gas on tankers of 8,000 DWT and over constructed from 1 January 2016 carrying Reg. 1.6.1 or Reg. 1.6.2 cargoes. Tankers constructed 1 July 2002 to 31 December 2015 stay at 20,000 DWT.
Revised FSS Code Chapter 15 (MSC.367(93)) applies to keels laid from 1 January 2016 via Chapter 1 para. 1.2 (MSC.292(87)). Plants must supply 125% max discharge rate by volume at 5% O2 max, auto-vent above 5% O2, and hold inerted tanks at or below 8% O2.
At least two deck non-return devices guard gas-safe spaces: a deck water seal (fed by two separate pumps with a continuous low-level alarm) or, from 1 January 2016, an automatic DBB unit. A positive-closure NRV or equivalent provides the second barrier.
IMO Resolution A.1207(34) guides annual IGS alarm and calibration checks under (EA) 1.2.3.2 and sets internal deck-seal examination and NRV condition checks at Renewal Survey (ER) 1.4.3.2. Under A.1206(34) Appendix 2, IGS operating or maintenance failure justifies halting cargo work.
Inert Gas Baselines under SOLAS Chapter II-2 and FSS Code Chapter 15 (2002 to 2015 vs 1 Jan 2016 Onwards)
Compliance Topic
2002 to 2015 Baseline (MSC.99(73) & MSC.98(73))
1 Jan 2016 Onwards (MSC.365(93) & MSC.367(93))
Engine-Room Check Focus
Tanker DWT & cargo scope (SOLAS II-2/4.5.5.1)
20,000 DWT and over (1 Jul 2002 to 31 Dec 2015, MSC.98(73)), plus COW tankers from 1 Jul 2002 (4.5.5.1.3).
8,000 DWT and over from 1 Jan 2016 carrying Reg. 1.6.1 or 1.6.2 cargoes, plus COW tankers (4.5.5.1.2, 4.5.5.1.3).
Confirm keel date, Certificate of Fitness, and pre-2016 chemical or gas-carrier exemptions (4.5.5.2.1).
High-O2 alarm & venting action
High-O2 alarm above 8% O2 (MSC.98(73) 2.4.3.1.5). Crew restore gas and pause tank ops above 8% (2.3.1.6).
High-O2 alarm above 5% O2 (2.2.4.5.1.1), auto-venting to atmosphere above 5% (2.2.2.4), and SOLAS II-2/16.3.3.3.
Test O2 analysers with calibration gas, prove auto-vent stroke past 5% O2, and verify CCR plus ECR meters.
Deck backflow barrier & seal alarm
Water seal required first (MSC.98(73) 2.3.1.4.1). Low-level alarm required in service (2.4.3.1.7) and when IG stops (2.2.4.6).
Deck water seal or automatic double block and bleed (2.2.3.1.2). Low-level alarm stays active at all times where fitted (2.2.3.1.4).
Test both seal pumps individually, check loop vacuum protection, and inspect seal internals plus NRV at Renewal (ER) 1.4.3.2.
Flue-gas / IGG vs N2 plant space
Allowed flue gas, gas generators, or Flag-accepted sources (2.2.1.1). Flag could permit one IGG fuel pump with spares (2.2.1.4).
IGG needs two fuel pumps (2.3.1.1.1) and positive-pressure room ventilation outside machinery spaces (2.3.1.1.2). Separate N2 rooms need 6 ACH extraction (2.4.1.3).
When two blowers are fitted from 2016, confirm even split with neither under one-third total (2.3.1.4.3), soot interlock (2.3.1.5), and N2 air treatment (2.4.1.2).
Room O2 sensors & low main pressure
Low IG pressure alarm under 100 mm WG (2.4.3.1.8) plus independent alarm or pump trip (2.4.3.4). No room O2 clause.
Low main pressure under 100 mm WG (2.2.4.5.1.3), separate alarm or pump trip (2.2.4.5.3), and two room O2 sensors below 19% (2.2.4.5.4).
Verify both room O2 sensors alarm inside and outside the compartment and audit permanent pressure and O2 recorder traces.
Overpressure, vacuum & tank purging
SOLAS II-2/11.6.3.4 P/V breaker limits vacuum to 700 mm WG on blower failure. Purge below 2% HC vapour (16.3.2.1).
Same 11.6.3.4 and 16.3.2.1 limits. FSS Ch. 15 2.2.3.2.3 adds spool removal or twin-spectacle blanks for un-inerted tanks.
Check P/V breaker fluid level and density where liquid-filled, 20 m/s purge outlets (4.5.6.3), and 250 mm bolted flange (2.2.3.2.6).
1. SOLAS II-2/4.5.5, 16.3.3 & FSS Code Chapter 15 Baselines (2002 to 2015 vs 1 Jan 2016 Onwards)
Tanker inert gas readiness begins by confirming which statutory edition governs the hull. IMO adopted Resolution MSC.365(93) on 22 May 2014 (effective 1 January 2016), replacing SOLAS II-2/4.5.5 and adding operational rule 16.3.3. Resolution MSC.367(93) replaced FSS Code Chapter 15 on the same date. Under FSS Code Chapter 1 paragraph 1.2 (amended by MSC.292(87)), FSS revisions adopted after 1 July 2002 apply to keels laid from the amendment entry date unless expressly stated otherwise.
Under SOLAS II-2/4.5.5.1.1, tankers of 20,000 DWT and over constructed between 1 July 2002 and 31 December 2015 require a fixed IGS meeting MSC.98(73), unless Flag-approved equivalents apply under 4.5.5.4. Regulation 4.5.5.1.2 drops that cutoff to 8,000 DWT and over for hulls constructed from 1 January 2016 carrying Reg. 1.6.1 or Reg. 1.6.2 cargoes. Scope spans petroleum with closed-cup flashpoint up to 60 °C and Reid vapour pressure below atmospheric pressure (1.6.1), plus higher-hazard liquid cargoes or liquefied gases (1.6.2). Older hulls of 8,000 to less than 20,000 DWT face no 4.5.5.1.2 retrofit unless operating crude oil washing.
Crude oil washing mandates fixed inert gas and fixed tank-washing machines regardless of deadweight. Regulation 4.5.5.1.3 covers COW tankers constructed from 1 July 2002, applying MSC.98(73) to 2002 to 2015 hulls and revised Chapter 15 from 1 January 2016 (older vessels remain under pre-2002 SOLAS II-2). Regulation 4.5.5.1.4 requires tankers obligated to carry IGS to fit double-hull inerting connections, blocking cargo hydrocarbon entry where permanently piped and providing connection arrangements otherwise. Tankers fitted with fixed IGS also require closed ullage systems (4.5.5.3.2).
Regulation 4.5.5.2.1 covers chemical tankers and gas carriers. Chemical tankers built before 1 January 2016 and gas carriers need not apply FSS Chapter 15 when they meet the Administration's chemical-tanker IGS rules, based on IMO guidelines, for Reg. 1.6.1 cargoes. The same exemption covers other flammable cargoes, such as IBC Chapter 17 or 18 products, within three caps. Tanks hold no more than 3,000 cubic metres, each washing nozzle delivers no more than 17.5 cubic metres per hour, and the machines in one tank together stay within 110 cubic metres per hour. The text names all gas carriers, but Reg. 1.2.8 ties 4.5.5.2.1 to ships built before 1 January 2016, so confirm the position with the flag for a newer gas carrier. For tankers of 8,000 to under 20,000 DWT built from 1 January 2016, Reg. 4.5.5.4.2 lets the flag accept equivalent protection under Regulation I/5 and 4.5.5.4.3.
The operating rules in SOLAS II-2/16.3.3 depend on build date (Reg. 1.2.7). Clauses 16.3.3.1, 16.3.3.2 and 16.3.3.4 apply to every tanker that must carry IGS, old or new. The plant must keep the cargo tank atmosphere non-flammable unless a tank must be gas-freed (16.3.3.1). Chemical tankers may inert after loading and before discharge, using nitrogen only, until the tank is purged before gas-freeing (16.3.3.2). If the plant fails and repair is impractical, discharge or tank cleaning restarts only after the emergency procedures in IMO guidelines (16.3.3.4).
Clause 16.3.3.3 applies only to tankers built from 1 January 2016. If the inert gas goes above 5% oxygen, the crew act at once to correct it. If it does not improve, stop all operations in the tanks being supplied, shut any gas regulating valve, and vent the off-spec gas. Tankers carrying only petroleum with a closed-cup flashpoint above 60 °C follow Reg. 1.6.4 instead of the Reg. 4.5.5 IGS rules. Every tanker needs an IGS maintenance plan (SOLAS II-2/14.4.1) and the FSS manuals (Ch. 15 para. 2.2.5, or para. 2.4.4 under MSC.98(73)).
Verify hull keel date, cargo scope (SOLAS II-2/1.6.1, 1.6.2, or 1.6.4), and whether MSC.98(73) or MSC.367(93) applies to the Safety Equipment Certificate.
Inspect SOLAS II-2/4.5.5.1.4 double-hull inerting connections and closed ullage equipment (4.5.5.3.2) against approved drawings.
Confirm the SOLAS II-2/14.4.1 maintenance plan and FSS Code Ch. 15 para. 2.2.5 (or MSC.98(73) 2.4.4) manuals match installed plant.
Check standing orders apply chemical-tanker nitrogen rules (16.3.3.2) where used and 5% O2 suspension actions (16.3.3.3) on hulls constructed from 1 January 2016.
Under FSS Code Chapter 15 clause 2.2.1.2, every compliant IGS must supply at least 125% of maximum cargo discharge rate by volume while holding delivery oxygen at or below 5% by volume across required flow rates. For chemical or chemical-product tankers under MSC.367(93) 2.2.1.2.4, Flags may accept lower output provided maximum protected-tank discharge rate stays capped at 80% of IGS capacity. Inerted tanks must remain at or below 8% oxygen by volume under positive pressure except during gas-freeing. On flue-gas units, typical causes of high oxygen include excess boiler air, leaking uptake ducts, suction seal leaks, or analyser drift.
Uptake isolation and soot control protect both scrubber and engine room before hot flue gas enters cooling stages. Clause 2.3.1.5 requires flue-gas isolating valves between boiler uptakes and the scrubber with open-closed indicators and soot protection on valve seats. An interlock must prevent boiler soot blowers from running while the matching flue-gas valve stands open, so soot blowing never happens while that boiler's flue gas is being drawn towards the scrubber. For safe internal work while boilers operate, clause 2.3.1.6.2 requires a second water seal or other effective leakage barrier between uptake valves and the scrubber, or built into scrubber gas entry.
Inside flue-gas and oil- or gas-fired inert gas generator scrubbers, clause 2.3.1.3.1 mandates effective cooling plus solids and sulphur removal. Cooling water must stay continuously available without disrupting essential ship services, backed by an alternative cooling-water source. Dissolved sulphur dioxide creates acidic washwater that attacks steel casings, spray nozzles, tray plates, and overboard effluent spools. Across all IGS types from 1 January 2016, clause 2.2.1.3 mandates corrosion-resistant materials or linings such as rubber or glass-fibre epoxy resin on surfaces exposed to corrosive gas or liquid.
Scrubber cooling drops when spray nozzles foul, headers loosen, or packing collapses. Weak gas-to-water contact pushes discharge gas temperature toward the high-temperature shutdown setpoint in the maker manual. FSS Code Chapter 15 sets no universal numeric trip temperature in degrees Celsius. Clauses 2.2.2.2, 2.3.2.1, and 2.3.2.2.5 instead require continuous discharge temperature indication and automatic shutdown at predetermined installation limits. Low cooling-water pressure or flow (2.3.2.2.3) and high scrubber water level from blocked effluent drains or seized overboard valves (2.3.2.2.4) also trigger alarms and trips.
Water carried over from the scrubber is a typical cause of blower damage. Clause 2.3.1.3.2 requires filters or similar mist pads, called demisters on board, to limit the droplets reaching the blowers. A fouled or collapsed demister raises scrubber differential pressure and lets acidic mist coat the impellers with salt, leading to vibration, bearing wear and hub cracks. At least two blowers are required (2.3.1.4.1). From 2016, two blowers share the load evenly, neither below one-third (2.3.1.4.3). For IGG systems the flag may accept one full-size blower if the crew carry spares to repair it (2.3.1.4.1).
Inert gas generators have three stricter rules from 1 January 2016 under MSC.367(93). An oil-fired IGG needs two fuel-oil pumps, ending the old single-pump-with-spares option (2.3.1.1.1). Positive-displacement IGG blowers need a pressure relief device on the discharge side (2.3.1.4.2). The IGG sits outside the cargo area with no direct access from accommodation, service or control spaces; outside a machinery space it needs a gastight steel boundary and positive-pressure ventilation (2.3.1.1.2). The gas regulating valve is fitted on the front bulkhead of the foremost gas-safe space on the main's route and closes automatically on a shutdown (2.3.1.2).
Inspect flue-gas isolating valve seats, actuators, and boiler soot-blower interlocks (2.3.1.5) prior to inerting or purging.
Trend scrubber differential pressure, cooling-water pressure, and overboard drain valves, inspecting internal linings at planned openings.
Fresh-water wash blower casings after service per maker instructions, trend impeller vibration, and inspect demisters for fouling or collapse.
Verify two oil-fired IGG fuel pumps (2.3.1.1.1), alternative scrubber cooling supply (2.3.1.3.1), and PD-blower pressure relief (2.3.1.4.2) on ships built from 1 January 2016.
Blocking flammable cargo vapour and liquid from flowing back into the inert gas plant or gas-safe spaces is a core IGS safety function. FSS Code Chapter 15 clause 2.2.3.1.1 calls for a minimum of two backflow barriers, and clause 2.2.3.1.9 places them on deck in the cargo area. Under clause 2.2.3.1.8, the primary deck seal (or equivalent barrier) and its water loops must resist vapour and liquid backflow up to cargo tank test pressure. Crews must never bypass or operate with degraded deck backflow barriers during cargo transfer, ballasting, or tank washing.
Under MSC.367(93) clause 2.2.3.1.2, the primary deck barrier may be a deck water seal (wet, semi-wet, or dry design) or an automatic double-block-and-bleed assembly using two series shut-off valves with a central vent. Double-block-and-bleed valves must actuate automatically from direct process signals such as differential pressure or inert-gas flow, sounding an alarm on faulty logic like blower stop with open supply valves. Clause 2.2.2.6 adds fail-safe power-loss action: both block valves shut automatically while the bleed opens. Tankers built from 2002 to 2015 under MSC.98(73) had no Chapter 15 DBB option and required a water seal.
Deck water seals depend on reliable seal-water flow, intact loop drains, and controlled winter heating. Clause 2.2.3.1.4 requires a water seal, where fitted, to be capable of supply by two separate pumps, each maintaining adequate flow continuously, with an audible and visual low-level alarm active at all times. Under MSC.98(73) (2.4.3.1.7 and 2.2.4.6), the low-level alarm was required during operation and also when inert gas was stopped. Clause 2.2.3.1.7 mandates water loops or approved equivalents on supply, drain, vent, and sensing pipes entering gas-safe spaces, with protection against vacuum emptying. Freeze protection must never impair seal integrity through overheating (2.2.3.1.6).
Wet and semi-wet deck seals can degrade through four typical hardware faults. Corroded submerged dip tubes or venturi baffles let vapour bypass the water column, while blocked drain loops push water into the IG main. Damaged demister pads carry salt spray onto deck valves, and sticky floats mask low seal water. The second barrier (2.2.3.1.3) is a mechanical non-return valve, or a device that does the same job, fitted between the deck seal or DBB unit and the first cargo-tank branch. It must carry positive closure, or an extra positive-closure isolating valve must sit between the NRV and the first tank branch.
Distribution piping downstream of (forward of) the deck barriers follows strict isolation standards under clause 2.2.3.2 (amended by MSC.457(101), effective 1 January 2024, replacing forward of with downstream of). Where cargo-tank branch stop valves are fitted, they need locks and clear open-closed status on the 2.2.4 control panel (2.2.3.2.2). Under MSC.367(93) 2.2.3.2.3, any un-inerted tank must isolate from the IG main via spool removal and blanking, twin spectacle flanges with intermediate leak detection, or a Flag-approved equivalent. Clause 2.2.3.2.6 requires a bolted 250 mm nominal bore external supply flange downstream of (forward of) the NRV behind an isolating valve. Cargo-main links need two shut-off valves with safe intermediate venting or blanked spools plus a positive-closure NRV on the cargo side (2.2.3.2.7, 2.2.3.2.8).
Cargo-tank pressure and vacuum limits sit in SOLAS rather than in FSS Chapter 15. FSS clause 2.2.3.2.4 only asks for protection of isolated tanks against thermal and cargo-operation pressure changes. SOLAS II-2/11.6.3.4 requires P/V breaking devices on the IG main, unless they are in the Reg. 4.5.3.1 vent system or on each tank. They keep tank pressure below test pressure when loading at full rate with other outlets shut, and vacuum within 700 mm water gauge should the blowers stop during full-rate discharge. Keep liquid-filled breakers at the maker's level and density.
Where a deck water seal is fitted, test both separate supply pumps individually and confirm the low-level alarm works running and stopped (2.2.3.1.4).
Inspect seal drain loop pipes, vacuum-emptying protection (2.2.3.1.7), and winter heating controls so freezing is prevented without overheating (2.2.3.1.6).
On DBB installations, test power-loss fail-safe during planned maintenance to confirm both block valves close and the bleed opens automatically (2.2.2.6).
Check P/V breaker settings (and fluid level, specific gravity, and freeze point where liquid-filled), plus the 250 mm external flange and branch-valve locks.
Revised FSS Code Chapter 15 added technology-neutral Section 2.4 for nitrogen generator plants alongside Section 2.2 general rules. Clause 2.4.1.1 mandates one or more compressors supplying enough positive pressure to meet full 2.2.1.2 gas volume. Clause 2.4.1.2 requires feed-air treatment removing free water, solid particles, and oil traces upstream of separation modules. Oil mist or liquid water carry-over fouls separation cartridges and can push nitrogen oxygen content past the 5% auto-vent threshold.
Compartment fire and ventilation rules for nitrogen plants differ from inert gas generator spaces. Under clause 2.4.1.3, compressors and nitrogen units may sit inside the engine-room or inside a dedicated compartment classed for fire protection as an other machinery space. Separate rooms must not open directly into accommodation, service, or control spaces and need independent mechanical extraction at 6 air changes per hour. Under clause 2.4.1.4, nitrogen receivers or buffer tanks may sit in a dedicated room, the separate generator room, the engine-room, or cargo area. Inside any enclosed space, access must be from open deck through an outward-opening door with independent extraction. By contrast, IGG spaces outside machinery spaces require positive-pressure mechanical ventilation (2.3.1.1.2).
Continuous indicators and permanent recorders create the main audit record reviewed during surveys and port calls. Clauses 2.2.4.2 and 2.2.4.3 require continuous indication and permanent recording whenever inert gas flows for two values: IG main pressure downstream of (forward of) deck non-return devices (per MSC.457(101)), and inert gas oxygen content. Both displays must sit inside a fitted cargo control room, or at an accessible cargo-officer station where no CCR exists. Clause 2.2.4.4 adds a navigating-bridge meter showing IG main pressure at all times (plus isolated combination-carrier slop-tank pressure), and an engine-room or MCR oxygen readout. Flue-gas and IGG plants show discharge-side temperature (2.3.2.1), whereas nitrogen generators show suction-side air pressure and temperature (2.4.2.1).
MSC.367(93) separates audible and visual alarms into universal and plant-specific tiers. Clause 2.2.4.5.1 covers all plants: oxygen above 5% by volume, indicator power failure, IG main pressure under 100 mm water gauge, high main pressure, and auto-control power failure. High oxygen, low pressure, and control-power alarms must sound in both cargo control and machinery spaces (2.2.4.5.2). Clause 2.2.4.5.3 requires an independent audible alarm or automatic cargo-pump shutdown at predetermined low IG main pressure limits. Clause 2.2.4.5.4 adds two oxygen sensors positioned appropriately in the space or spaces housing the IGS, activating audible and visual alerts inside and outside below 19% oxygen.
Plant-specific alarms sit in clauses 2.3.2.2 and 2.4.2.2. Flue-gas and IGG plants have seven: low IGG fuel, generator power loss, low scrubber water flow or pressure, high scrubber water level, high gas temperature, blower failure, and low deck-seal water where a seal is fitted. Nitrogen plants have four: heater failure (if fitted), low compressor air flow or pressure, high air temperature, and high condensate at the separator drain. MSC.367(93) dropped the old MSC.98(73) portable-meter clauses (2.4.2.4, 2.4.2.5). SOLAS II-2/4.5.7.1, as amended by MSC.291(87), still requires portable oxygen and flammable-vapour meters and a way to calibrate them, checked under A.1207(34) (EA) 1.2.3.5 and (EA) 1.2.3.2.12.6.
Tank purging and gas-freeing connect engine-room plant operation to deck cargo safety under SOLAS II-2/4.5.6 and 16.3.2.1. Before introducing fresh air into an inerted tank, Regulation 16.3.2.1 mandates purging under 4.5.6 until hydrocarbon vapour drops below 2% by volume, after which gas-freeing may proceed at deck level. Under Regulation 4.5.6.3, individual cargo-tank purge outlet pipes (if fitted) place their inlet at deck level or within 1 metre of tank bottom and rise at least 2 metres above deck. They carry suitable blanking arrangements and maintain at least 20 metres per second exit velocity when supplying any three tanks simultaneously. Non-IGS tanker gas-freeing rules (30% LFL and 30 or 20 m/s outlets) sit separately in 16.3.2.2 to 16.3.2.4.
Inspect nitrogen coalescing filters, separator auto-drains (2.4.2.2.4), electric heater controls where fitted (2.4.2.2.1), and 6 ACH extraction fans where housed separately (2.4.1.3).
Test and calibrate both room oxygen sensors to verify audible and visual alarms trigger below 19% O2 inside and outside the IGS space(s) (2.2.4.5.4).
Confirm purge-pipe blanking arrangements (4.5.6.3.3) remain tight during inerting and verify hydrocarbon vapour drops below 2% by volume (16.3.2.1) before gas-freeing.
5. Enclosed-Space Entry, Inert Gas Asphyxiation & MSC.581(110) Guidance
Inert gas works by removing oxygen, so a leak into an IGS room, a nitrogen buffer room or a nearby void can kill. IMO Resolution MSC.581(110) of 27 June 2025 is guidance rather than treaty law. It sits alongside the mandatory enclosed-space rescue drills (SOLAS III/19.3.6), the atmosphere-testing instruments (SOLAS XI-1/7) and the company's ISM procedures. Paragraph 1.1 lists inert gas rooms, compressor rooms and pump-rooms among the working spaces where a dangerous atmosphere can build up. Paragraph 10.2.2 warns that nitrogen has no colour or smell, and that one deep breath of pure nitrogen can kill.
Before opening a scrubber, a deck-seal casing or a nitrogen buffer room, check that the space is in the ship's Enclosed Space Register (paras. 2.8 and 4.1). Isolate every connecting line first (6.5.1): uptake valves, the second scrubber seal (FSS 2.3.1.6.2) and deck stop valves. Stop the ventilation for about 10 minutes, then test at several levels (7.2, Appendix 2). Enter only on steady readings of 20.9% oxygen, under 0.5% carbon dioxide, under 1% LFL and under 50% of the OEL for toxic gases (7.4). National rules may set different figures.
The risk assessment sets how long the permit lasts, never more than 8 hours (5.2). The permit lapses if the space is left unattended or conditions change (Appendix 2), and the atmosphere is retested after any break (8.3). Nobody should enter alone (3.11). In an emergency the attendant waits for help (8.5). Rescuers wear positive-pressure breathing apparatus, never filter masks or EEBDs (9.2), with harnesses and, where practicable, lifelines (9.4).
Confirm every IGS room, nitrogen buffer room and adjacent void is in the Enclosed Space Register (MSC.581(110) paras. 2.8, 4.1).
Isolate connecting lines before entry (6.5.1) and stop ventilation for about 10 minutes before testing (Appendix 2).
Record steady 20.9% O2, under 0.5% CO2, under 1% LFL and under 50% OEL at several levels (7.2, 7.4).
Set the permit period by risk assessment (never over 8 hours, 5.2) and keep tested breathing apparatus and rescue gear at the entrance (6.5.8).
6. HSSC Surveys (A.1207(34)), PSC Procedures (A.1206(34)) & Technical Support
IMO Resolution A.1207(34) (3 December 2025) sets the survey scope. At the Initial Survey, items (EI) 1.1.2.1 and 1.1.8.1 cover the cargo-tank protection plans and the FSS Code 2.2.5 manuals. Items (EI) 1.1.5.2.1 to 1.1.5.2.13 then test the plant itself. They cover leaks, both blowers, scrubber-room ventilation, deck-seal filling and freeze protection, the DBB fail-safe, flue-gas valves and soot-blower interlocks, the two room O2 alarms, the simulated alarm list with O2 calibration gas, and a final run.
At every Annual Survey (EA) and Periodical Survey (EP 1.3.1.1, 1.3.3.1), surveyors review IGS manuals alongside pressure and oxygen operating logs under (EA) 1.2.1.15. Annual hardware items (EA) 1.2.3.2.1 to 1.2.3.2.12.10 verify the same components plus simulated alarm, safety-device, and O2 calibration-gas accuracy checks ((EA) 1.2.3.2.12.6), followed by operational testing when practicable under (EA) 1.2.3.3. Separate Safety Construction Annual items (CA) 2.2.3.3 and 2.2.3.5 cover oil tankers (extended to chemical tankers and gas carriers via (CA) 2.2.4.1, and repeated at Intermediate and Renewal surveys). Those items cover cargo-tank P/V valves and flame screens (SOLAS II-2/11.6), plus the tank venting, purging and gas-freeing arrangements and other ventilation (regs. 4.5.3, 4.5.4, 4.5.6, 4.5.8).
At the five-yearly Renewal Survey, surveyors carry out all Annual and Periodical IGS items ((ER) 1.4.1.1, 1.4.3.1) plus one Renewal-only scope. Under A.1207(34) item (ER) 1.4.3.2, surveyors examine the deck water seal internally and check non-return valve condition (citing FSS Code Chapter 15 paragraphs 2.2.3.1 and 2.3.1.6.2). Annual and Periodical HSSC guidelines do not include internal deck-seal examination or NRV condition inspection. Superintendents should align gas-freeing, dip-tube inspection, elastomer seal kits, and NRV seat refurbishment directly with five-year renewal drydocking.
The PSC procedures in Resolution A.1206(34) (3 December 2025) separate stopping cargo work from detaining the ship. Appendix 2 gives examples rather than a closed list, and the PSC officer makes the judgement. An inert gas system that is not working or not maintained is listed as grounds to stop cargo operations rather than to detain. Detention examples include failed cargo-deck fire protection on tankers (SOLAS item 7), missing non-sparking pump-room exhaust fans (item 12) and serious ISM failures (ISM item 1).
During in-port crude oil washing inspections, A.1206(34) Appendix 3 Part 4 reviews IGS records across sections 4 and 5. Section 4 (.4) expects the Safety Equipment Certificate to confirm SOLAS Chapter II-2 IGS conformity, while clause 5.1 notes checking the permanent supply-main pressure and oxygen recorder shows whether the plant operated satisfactorily before and during discharge. Under clause 5.2, washing must stop if approved COW Manual conditions are not met until compliant parameters return. Under clause 5.3, oxygen levels before washing each tank are checked at the tank with calibrated, inspected meters in good order, keeping prior in-port tank wash records ready for verification and possible spot checks.
When persistent high-oxygen trips, scrubber lining corrosion, deck-seal siphoning, or nitrogen feed-air fouling threaten off-hire or survey readiness, Marvel Solutionz supports engineering teams directly. Book a remote diagnostic session at $350 USD for a 1-hour consultancy (+ 5% sales tax). Enrol in the LNG, Dual-Fuel & Spark-Gas Academy at $395 USD self-paced (+ 5% sales tax) with a 5-minute free Lab 01 simulator trial. Corporate Team Training for up to 10 engineers is available at $3,500 USD (+ 5% sales tax).
Compile an Annual survey pack with (EA) 1.2.1.15 pressure and O2 records, calibration gas ((EA) 1.2.3.2.12.6), and the nine remaining (EA) 1.2.3.2.12 alarm and safety-device checks.
Schedule internal deck water seal examination, dip-tube inspection, and mechanical NRV condition overhaul into the five-year Renewal Survey (ER) 1.4.3.2 dock spec.
Audit permanent supply-main pressure and O2 recorder records, meter calibration and inspection status, and in-port tank O2 readings against the COW Manual per A.1206(34) Appendix 3 Part 4 section 5.
Verify cargo-tank P/V valves, flame-passage prevention devices, and venting, purging, and gas-freeing arrangements ahead of Safety Construction surveys under A.1207(34) (CA) 2.2.3.3 and 2.2.3.5.
Frequently Asked Questions
Which tankers require a fixed inert gas system under SOLAS II-2/4.5.5?
Under SOLAS II-2/4.5.5.1, tankers of 20,000 DWT and over built from 1 July 2002 to 31 December 2015 need a fixed IGS to MSC.98(73). From 1 January 2016 the threshold drops to 8,000 DWT for Reg. 1.6.1 or 1.6.2 cargoes, under revised Chapter 15. A tanker that uses crude oil washing needs IGS whatever its size (4.5.5.1.3). Exemptions and equivalents sit in 4.5.5.2 and 4.5.5.4.
What is the difference between the 5% and 8% oxygen limits in FSS Code Chapter 15?
Under FSS Code Chapter 15 (MSC.367(93)), 5% oxygen by volume is the upper delivery limit in the supply main (2.2.1.2.5), while above 5% triggers the high-oxygen alarm (2.2.4.5.1.1) and automatic venting to atmosphere (2.2.2.4). The 8% oxygen by volume ceiling governs inerted cargo-tank atmospheres under positive pressure except when gas-freeing (2.2.1.2.1).
Does FSS Code Chapter 15 allow double block and bleed instead of a deck water seal?
Yes on hulls constructed from 1 January 2016 under MSC.367(93) clause 2.2.3.1.2, provided direct process signals operate the valves automatically, faulty valve logic triggers an alarm, and power loss closes both block valves while opening the bleed (2.2.2.6). Hulls built 2002 to 2015 under MSC.98(73) had to fit a deck water seal.
What pressure limits govern cargo-tank P/V breakers under SOLAS Chapter II-2?
SOLAS II-2/11.6.3.4 requires P/V breaking devices preventing positive pressure above cargo tank test pressure during loading at maximum rated capacity with all other outlets left shut. They must also stop negative pressure exceeding 700 mm water gauge if cargo pumps discharge at maximum rated capacity while inert gas blowers fail.
Does a failed inert gas system automatically cause PSC detention under A.1206(34)?
No. A.1206(34) Appendix 2 gives examples for the PSC officer's judgement, not automatic triggers. It lists a failed or poorly maintained IGS as grounds to stop cargo work rather than to detain. Other faults, such as failed cargo-deck fire protection on a tanker (SOLAS item 7) or a serious ISM failure, can still lead to detention.
Try the LNG, Dual-Fuel & Spark-Gas simulator free for 5 minutes, then enrol in the Academy: Self-Paced $395 USD or 6-Week Cohort $995 USD (+ 5% sales tax). Or book a 1-hour consultancy for $350 USD (+ 5% sales tax).
Enquiries welcome at any time. Book our daily 1-hour consultation at 12:00 PM Central Time (CT) ($350 USD + 5% sales tax) or send an enquiry about your vessel, power plant or project.
Have an Academy Access Key? Sign in on this page to send comments or questions straight to our instructors.
/guides/inert-gas-system-scrubber-deck-water-seal-and-fss-code-guide/